virtuous1
Oct 20, 2007, 08:18 PM
Can someone please help me with the solution to this problem. Project K costs $52,125, its expected net cash inflows are $12,000 per year for 8 years, and its WACC is 12%. What is the projects NPV?
I know the IRR is 16%, but how do I get this solution? And the same for the payback period, which I know is 4.34 years?
I know the IRR is 16%, but how do I get this solution? And the same for the payback period, which I know is 4.34 years?