Overhead cost: 1,000,000 budgeted 950,000 actual. Machine hours: 50,000 budgeted 45,000 actual. Direct labor hours: 100,000 budgeted 92,000 actual. Q: overhead is applied on basis of direct labor hours. Compute the predetermined overhead rate.

paraclete
Sep 21, 2013, 05:57 PM
Are you looking to carry out cost estimation of variance reporting

Actual results are anecdotal only in answering the question. This is not activity based costing but absorption costing methodology