During the recent month the following average times were recorded per order:
Wait Time: 15.6
Inspection Time: 0.8
Process Time: 1.6
Move Time: 0.7
Queue Time: 3.9
Required:
Compute the throughput time.
Compute the manufacturing cycle efficiency (MCE).
What percentage of the production time is spent in non-value-added activities?
Compute the delivery cycle time.
Wait Time: 15.6
Inspection Time: 0.8
Process Time: 1.6
Move Time: 0.7
Queue Time: 3.9
Required:
Compute the throughput time.
Compute the manufacturing cycle efficiency (MCE).
What percentage of the production time is spent in non-value-added activities?
Compute the delivery cycle time.