ur1payne
Nov 8, 2010, 08:08 AM
I have a 150a rated incomming service. I want to install a genready loadcenter that is only available with a 200 a main breaker installed. Do I have to use the 200a main or can I install a 125a double pole breaker in the branch breaker section and backfeed the bus and not use the 200a main? The existing panel is being done this way with a 60a double pole. But it is a main lug panel.