Rough Plumming

I Am Putting A Bathroom In My Basement. I Am Curious How Far The Closet Flange Should Be From The Back Wall And Does It Have To Be Flush With The Concrete. I Have The Old Concrete Cut Out Where The New Pvc Pipes Are And I Want To Make Sure I Have Everything In The Right Place Before I Fill The Hole Back In.

Reply With Quote
 
     

Answers
 
 
Old Feb 20, 2006, 12:21 PM   #2  
Full Member
PalmMP3 is offline
 
PalmMP3's Avatar
 
Join Date: Jan 2006
Location: New York City (although currently overseas)
Posts: 322
PalmMP3 See this member's comment history on his/her Profile page.
Call PalmMP3 via Skype™ Send a message via MSN to PalmMP3
The center of the flange should be 12" from the unfinished wall (or 11˝" from a sheetrock-finished wall). Height doesn't really matter; it can be resting on the floor, or even a bit below (but not higher than the floor level) - the main thing is that the two bolts can hook the toilet (to keep it from rocking back and forth). The flange does nothing other than secure the toilet to the floor; discharge is accomplished by the 4" "horn" on the bottom of the toilet, which goes through the flange and into the closet elbow. In fact, in the olden days, flanges weren't even used - the toilet was bolted directly to the floor.

Cheers
Moishe
Note: if this post was helpful, please rate it by clicking "Comment on this Post" in the upper-right corner of this post. Thank you.
  Reply With Quote
 
     
 
 
Old Feb 20, 2006, 12:23 PM   #3  
Senior Plumbing Expert
speedball1 is offline
 
speedball1's Avatar
 
Join Date: Jan 2003
Location: Sarasota, Fl.
Posts: 19,004
speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.speedball1 See this member's comment history on his/her Profile page.
Pay to call speedball1 for advice ($.95/min)
Call speedball1 via Skype™
Quote:
Originally Posted by T_THOM76
I Am Putting A Bathroom In My Basement. I Am Curious How Far The Closet Flange Should Be From The Back Wall And Does It Have To Be Flush With The Concrete. I Have The Old Concrete Cut Out Where The New Pvc Pipes Are And I Want To Make Sure I Have Everything In The Right Place Before I Fill The Hole Back In.
For a closet rough in, figure 12" from the plate of a unfinished wall or 11 1/2" from a finished wall.
The flange may be a little below the floor line but MUST be at least set flush on top of the floor but no higher. good luck, tom
  Reply With Quote
 
     

Your Answer
Email me when someone replies to my answer
Join Login



Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes
Ask your question or search...



Similar Threads
DWV rough-in
(5 replies)
rough feet...
(3 replies)
Please help me get over this rough period
(74 replies)
Rough in under slab
(1 replies)
Slab Rough-In
(29 replies)

Thread Tools
Show Printable Version Show Printable Version
Email this Page Email this Page
Search this Thread

Advanced Search

Bookmarks





Copyright ©2003 - 2009, Ask Me Help Desk.
All times are GMT -8. The time now is 03:25 PM.