    Adding shower to existing lav over a slab
    I am looking to add a stall shower to an existing half bath. Over a slab... I have never done this before and considering doing it myself... I can sweat pipe and can do basic carpentry... I know I need to jackhammer the floor remove and tap into the toilet line... are there any special concerns that I need to be aware of.. . some questions I had were
    1. do I need to add a vent ( shower will be within five feet of toilet) and next to the toilet there is a vent going up through the roof
    2. I am assuming I will add a "Y" of some sort to the toilet... and how is this connection done... thanks in advance for your help
    Greg
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #2

    Apr 13, 2005, 06:18 AM
    Quote Originally Posted by tcb
    I am looking to add a stall shower to an existing half bath. over a slab.....I have never done this before and considering doing it myself....I can sweat pipe and can do basic carpentry..... I know I need to jackhammer the floor remove and tap into the toilet line..... are there any special concerns that I need to be aware of.... ...some questions I had were
    1. do I need to add a vent ( shower will be within five feet of toilet) and next to the toilet there is a vent going up thru the roof
    2. I am assuming I will add a "Y" of some sort to the toilet... and how is this connection done...thanks in advance for your help
    Greg
    Good morning Greg,

    1. do I need to add a vent ( shower will be within five feet of toilet) and next to the toilet there is a vent going up through the roof
    Code forbids you to discharge a major fixture, (such as a toilet) past a unvented minor one, (such as your shower) You MUST do one of two things.
    If you tie into the toilet main you must run a individual vent for the shower, or, you can tie the vent into the lavatory drain and the shower will wet vent through the lavatory vent.

    2. I am assuming I will add a "Y" of some sort to the toilet... and how is this connection done...
    Since you haven't told me what material your pipes are I can't give you specific instructions on how to tie it in as different pipes will use different methods and I haven't a set of plans to lay out the job so I can't be specific as to what fittings to use, however you will cut in a Wye or combination wye and eighth bend to the lavatory drain line to pick up the shower.

    Good luck, Tom

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Adding Shower To Existing Garden Tub! [ 5 Answers ]

I need some advice on how to add a shower to a beautiful existing garden tub we have in our master bath. The tub came with the house we bought back in 1990. We have carpet in our bath which has become old, stained, and a bit moldy and plan on re-doing the floor. However, the tub is a bit of a...

Adding a heater to an existing circuit. [ 3 Answers ]

I want to place a 240V electric base board heater in a room. In the adjacent room I have a conveniently placed electric wall oven by itself on a 50 Amp circuit with 8 gauge wire. The oven is only rated at 30 Amps and the heater at 4.5 amps. So, I want to run wire from the oven to where the...

Adding a concrete extension to an existing patio [ 2 Answers ]

I need to add an extension to my patio aprox 4'x4'. It needs to be 4" thick to support my AC unit. I need to know how to do it.

Using existing tub drain line in concrete slab [ 4 Answers ]

I am installing a new whirlpool tub in place of an existing conventional tub. The old sink drain terminates into a concrete slab. The new sink drain will be at least 2 feet from the old. What are my options? Is there anyway of tieing in the new drain into the old drain without taking up all the...

Adding new bath to concrete slab [ 3 Answers ]

Hi, We just purchased a home in L.A. built in the 60s that has a concrete slab construction. We want to add on a master bath to the house but I don't know how we would tie into the plumbing lines in this kind of a foundation. Do they actually pour concrete onto the pipes when the foundation is...


View more questions Search