Thank you labman - here's the rest of my ideas on the basement so far, please let me know if a good alternative:
- 8' Sheetrock as you say.
- Drylock on poured concrete walls. 1/2" Polystyrofoam (Dow) sheets over that between the wall and framing, paperless wallboard on top of this. Was all I was going to do, but now maybe an extra sheet of plastic between frame and wallboard?
- R19 paper faced out on 1/2 frammed section already (not below grade) - paperless wallboard on top of this.
- Between top of sheetrock and joists - use plastic with foam insulation.
- Some type of Drylock treatment for the floor (if any one has a good product to use / recommend please let me know).
- If and when I can afford (will do first with bathroom) use "Dricore" (
http://www.dricore.com) sections on top of painted floor. I do not have a basement drain internally - but think this will help.
The footings for my basement actually sit about 15' below my poured slab - and this is where the drains actually sit. There is some grading externally that will help a bit - but all in all it's usually dry, although the dehumidifier does fill up twice a day during the summer. I'm located in HotLanta.
Final touch is to tap into the furnace for two outlet / inlets for HVAC. This I think is most important.
My winter project ...