    I recently installed a hot tub where there is a home-run from the hot tub to a 50 amp 240v GFCI in my circuit breaker panel in the basement (I ran #6 wire for the black, red, white and green). Everything works fine. I now need to install a disconnect near the tub. I would like to confirm if it's okay to have the disconnect just for the two hots, i.e. the black and red wires and leave the neutral/white alone (so it remains uninterrupted)? Also, if I ground the disconnect box directly to the circuit breaker panel is that sufficient (i.e. the green home run to the hot tub will also be uninterrupted)?
    tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #2

    Aug 11, 2012, 03:30 AM
    If you can, somehow, leave the neutral unbroken passing through the disconnect, sure.

    I am not sure what you mean by: "Also, if I ground the disconnect box directly to the circuit breaker panel", by doing the same with the ground wire. How can it pass through the disconnect unbroken and still ground the metal box of the disconnect?
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #3

    Aug 11, 2012, 07:11 AM
    Quote Originally Posted by tkrussell View Post
    If you can, somehow, leave the neutral unbroken passing thru the disconnect, sure.

    I am not sure what you mean by: "Also, if I ground the disconnect box directly to the circuit breaker panel", by doing the same with the ground wire. How can it pass thru the disconnect unbroken and still ground the metal box of the disconnect?
    tkrussell: Thanks for your answer. To be clear, you're saying the neutral wire is okay to leave unbroken, correct?

    Re: your ground wire question, I'm planning on running a #12 bare copper right from the circuit breaker panel rather than cut the #6 ground to the hot tub. Here's the reason.

    When I ran the original wiring, I didn't plan for a disconnect. Fortunately, I had an LB in the middle of the conduit run that's about 12 feet from the planned disconnect location. At this point, the simplest - and least expensive - solution I came up with was to cut a hole in the LB, run a 1" conduit to the disconnect box, cut the two hot leads in the LB and then splice in a short #6 wire run for the pair of hot leads "to and from" the disconnect through the (new) conduit. I have spare #12 (bare) wire that can easily be pulled from the basement breaker panel that will provide my disconnect ground, hence my question.
    tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #4

    Aug 12, 2012, 03:09 AM
    Do not do what you plan with the #12. Cut the ground in the #6 cable. How many splices you plan to do in the 1 " LB?

    You will create more points of failure with all of these splices.

    Why not just terminate the LB to the new disconnect, and then continue on with new #6 wire to the tub?

    You plan will have DIY all over it.
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #5

    Aug 13, 2012, 11:54 AM
    Quote Originally Posted by tkrussell View Post
    Do not do what you plan with the #12. Cut the ground in the #6 cable. How many splices you plan to do in the 1 " LB?

    You will create more points of failure with all of these splices.

    Why not just terminate the LB to the new disconnect, and then continue on with new #6 wire to the tub?

    You plan will have DIY all over it.
    Thanks again tkrussell for your follow up.

    When you write do not run the #12 ground as planned (i.e. directly from the circuit breaker panel to the disconnect box), is there a safety issue? While I'm far from an expert, I thought a direct ground from the circuit breaker panel would be as good as it gets.

    Your suggestion to "... terminate the LB to the new disconnect, and then continue on with new #6 wire to the tub", while a good one, unfortunately is not an option given where the LB's location. So my only choice is to run a new (1") conduit as previously described. Additionally, 1" is the maxiumum knockout for the disconnect box. BTW, the LB is a 1 1/2" as is the original conduit run, so there's enough room for the splices in the LB. I plan on wrapping the wire nuts with electrical tape to help mitigate splice issues.

    The plan is to have a total of four splices in the 1 1/2" LB: two each for the two hot leads. See attached "Hot Tub wiring diagram".

    I appreciate your comment regarding "more points of failure" however, given my only option of a new conduit run, using the original #6 ground for the disconnect box will create another splice in the LB and that seems to exacerbate your point. Additionally, it will crowd the 1" (new) conduit to the disconnect, although I recognize the capacity for 1" conduit is 6 - #6 wires. This is why I thought the #12 independent ground from the circuit breaker panel directly to the disconnect box accomplishes both the grounding requirements and the crowded conduit concern.
    Attached Images
  1. File Type: pdf Hot Tub wiring diagram.pdf (229.2 KB, 134 views)
  2. tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #6

    Aug 14, 2012, 06:14 AM
    Running a separate ground wire, not part of a cable or enclosed raceway with the branch circuit conductors is not allowed by Code.

    Splicing in a condulet, such as an LB is only allowed if the volume of space is noted on the fitting, which problably is there considering it is a PVC unit. Next need to determine what space the wiring needs.

    #6 needs 5 cubic inches of space for each conductor. Your sketch shows 6-#6 wires to be spliced, so a total of 30 CI is needed, never mind the wires that run straight through the LB.

    What is the cubic inch of space of this LB?

    How about continuing from the LB to the tub, and then a conduit to the disconnect, do all connections in the tub connection box?
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #7

    Aug 14, 2012, 11:00 AM
    Quote Originally Posted by tkrussell View Post
    Running a separate ground wire, not part of a cable or enclosed raceway with the branch circuit conductors is not allowed by Code.

    Splicing in a condulet, such as an LB is only allowed if the volume of space is noted on the fitting, which problably is there considering it is a PVC unit. Next need to determine what space the wiring needs.

    #6 needs 5 cubic inches of space for each conductor. Your sketch shows 6-#6 wires to be spliced, so a total of 30 CI is needed, nevermind the wires that run straight thru the LB.

    What is the cubic inch of space of this LB?

    How about continuing from the LB tothe tub, and then a conduit to the disconnect, do all connections in the tub connection box?
    tkrussell: I greatly appreciate your expertise and ongoing responses on this.

    Doing the connections in the hot tub, unfortunately, is not an option either given the nature of the run, etc.

    I've attached a new drawing (Hot Tub wiring diagram-rev1) which eliminates the direct #12 ground wire from the circuit breaker panel to the disconnect. Instead, I am splicing the original (#6) ground within the LB and running a #6 ground lead through the 1" (new) conduit to the disconnect box. As you will see, this creates 5 splices in the 1 1/2" LB. Per the manufacturer's spec, the 1 1/2" LB volume is 32 cu. in... would that accommodate what the new diagram shows? Is this design within code?
    Attached Images
  3. File Type: pdf Hot Tub wiring diagram-rev1.pdf (37.9 KB, 142 views)
  4. tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #8

    Aug 14, 2012, 11:05 AM
    Stupid question, but can you change the LB to a junction box?

    Each wire that needs to be spliced require 5CI of space. Now you have ten, times 5 CI each, totals 50 CI needed, and the LB is much too small.

    How about some photos of the panel, LB local area.

    There has got to be a way without splicing in the LB.
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #9

    Aug 14, 2012, 12:09 PM
    Quote Originally Posted by tkrussell View Post
    Stupid question, but can you change the LB to a junction box?

    Each wire that needs to be spliced require 5CI of space. Now you have ten, times 5 CI each, totals 50 CI needed, and the LB is much too small.

    How about some photos of the panel, LB local area.

    There has got to be a way without splicing in the LB.
    I'm not at the property so can't get photos today. But I'm pretty darn sure given the location of the various items, the disconnect box knockout restrictions, what's already been run, etc. I have what I have (I'll see if I can quickly draw a to scale sketch of the layout and post that).

    Re: changing to a junction box, maybe, but that would require my cutting all the original wires (at this point it's really only cutting the white/neutral which, I guess is not a big deal). And then it would be cutting the original 1 1/2" conduit at each end of the LB. I suspect a big enough juction box would be larger than the LB so the conduit may still reach. Also that would mean having a separate 1" conduit to the disconnect and a separate 1" conduit from the disconnect. I'll have to look into this further (albeit, this switch is quite a pain but it's my own fault).

    If I understand how your calculating the 5 CI / spliced wire requirement, there may actually be 11 as follows: 2 black and 2 red going to the disconnect; 2 black and 2 red coming from the disconnect; and 3 green (look carefully at the "rev1" diagram again... the green is a three wire splice). So if I'm right with this, then if I have to cut the white, I'll be adding another 2 spliced wires which will bring the total to 13 spliced wires x 5 = 65 cu. in. junction box requirement. Do I have this right?
    tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #10

    Aug 14, 2012, 12:59 PM
    Yes, you have the wire fill calc correct.

    Do not let knockout size stop you, they can be made bigger, or smaller, and conduit can be made longer.

    If this LB is outside, the junction box will need to be either NEMA 3R or NEMA 4 rated, raintight or water tight.

    Photos will sure help figure this out. The splicing all of these #6 in an LB is not going to work.
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #11

    Aug 14, 2012, 02:58 PM
    See the attached drawing showing the diagram of conduit run + LB + disconnect + hot tub. Hopefully it gives you some additional perspective
    Attached Images
  5. File Type: pdf diagram of conduit run + LB + disconnect + hot tub.pdf (16.3 KB, 98 views)
  6. hfcarson's Avatar
    hfcarson Posts: 1,003, Reputation: 49
    Ultra Member
     
    #12

    Aug 15, 2012, 04:11 AM
    Interesting drawing... you're adding a conduit to an LB?
    Although very creative, this will never be approved by an inspector
    As it violates 110.3(B) which is listing and labeling. Equipment and materials
    Are required to installed and used as directed by their instructions...
    Replacing the LB with a junction box would eliminate a lot of issues... why not?
    tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #13

    Aug 15, 2012, 05:12 AM
    I saw the conduit that seems to enter the flat back of the LB, or at least looks like that.

    No, cannot do that.

    You need to figure out how to add a junction box, may need to re-pipe if necessary.

    I would really like to see some photos of the existing installation.
    Stratmando's Avatar
    Stratmando Posts: 11,188, Reputation: 508
    Uber Member
     
    #14

    Aug 15, 2012, 05:13 AM
    Can't you just have Power from house, and go to disconnect, and from Disconnect to SPA?
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #15

    Aug 15, 2012, 08:23 AM
    Quote Originally Posted by tkrussell View Post
    I saw the conduit that seems to enter the flat back of the LB, or at least looks like that.

    No, cannot do that.

    You need to figure out how to add a junction box, may need to re-pipe if necessary.

    I would really like to see some photos of the existing installation.
    I think I can do a spliceless solution without re-piping the conduit. It would mean pulling the original wires from the circuit box which is probably not too labor intensive.

    For the existing LB, the hole would be in the body, not the cover, which I assume that's what you thought. I'm a bit perplexed why it's okay to cut a hole in a junction box but not an LB? Is it what hfcarson said "...it violates 110.3(B) which is listing and labeling. Equipment and materials are required to installed and used as directed by their instruction"?
    tkrussell's Avatar
    tkrussell Posts: 9,659, Reputation: 725
    Uber Member
     
    #16

    Aug 15, 2012, 09:00 AM
    If you insert a conduit into the flat side of the LB, it will violate Code, and definitely look like a DIY job.

    Either concede to install a junction box, and/or re-pipe the job, or we cannot help any further.
    chebowitz's Avatar
    chebowitz Posts: 9, Reputation: 1
    New Member
     
    #17

    Aug 15, 2012, 09:25 AM
    Quote Originally Posted by tkrussell View Post
    If you insert a conduit into the flat side of the LB, it will violate Code, and definitely look like a DIY job.

    Either concede to install a junction box, and/or re-pipe the job, or we cannot help any further.
    I'll be installing the junction box. I found one that's NEMA 6P which seems to be even a higher standard.

    Thanks tkrussell for all your help, guidance and patience with this. What I thought was a simple question regarding wiring the disconnect properly became a learning experience about troubleshooting a tough situation. While it will be a little more work than anticipated, I know the job will be a good one. Thanks again tkrussell... you've done a great service.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Hot tub disconnect location [ 1 Answers ]

Location of the disconnect from the spa

Midwest hot tub disconnect box ground bar? [ 2 Answers ]

Hi All, I've recently taken on the adventure of setting up the basic wiring of a Midwest hot tub breaker box "service disconnect" with 50 AM GFCI breaker installed. The disconnect box I purchased has an aluminum bar (ground I assume) inside the box that can be connected (?) to one of the three...

I am installing a gfic breker for a hot tub. [ 1 Answers ]

Breaker keeps triping; I have a red,black, Neutral and ground, power coming in. The hot tub has the same wireing going to the gfic box. The neutral and the ground wires are hooked to the ground block, What have I hooked up wrong?

Installing a hot tub [ 1 Answers ]

I am moving my hot tub to my new house and I don't have a empy spot in electric box for anymore breakers and it's a 100 amp box they say I need to upgrade to a 200 amp box for about 1,500-2,000 any suggestions?? And the house I live in is not that old it was built in 2000 they just used the cheap...

Hot Tub Disconnect [ 4 Answers ]

From reading past questions and responses, I got a fairly clear idea about how to wire the GFI panel between the distribution panel and hot tub. Thanks for the references that people posted! There is still one requirement, however, that still puzzles me. The NEC calls for a disconnect to be...