eahudson88
Jul 12, 2010, 09:44 PM
The narrow gravel road to Jehnzen Lake is open only for the summer months. At present, the county spends $750 per mile each year to prepare the road for summer traffic and another $150 per mile for maintenance during the period in which it is open. A “permanent” road could be constructed at a cost of $10,000 per mile; the county would have to spend $800 per mile for maintenance (patching, etc.) only every 5 years through the 30 year life of the road. Prospects for the area suggest that the road would have to be relocated at the end of that period. If 8 percent is a reasonable discount rate, which option is least costly? What discount rate would cause the two alternatives to have the same cost in present-value terms?