Bell is the input side of SDR 35, right?

cdad
Jul 2, 2010, 06:57 PM
If your talking about a raised lip on the gasket then that goes on the side closest to the bottom of the lip. It's there to prevent backflow.

http://www.plastictrends.com/products/pdf/G_Series.pdf

KISS
Jul 2, 2010, 07:13 PM
No this stuff: http://www.lowes.com/pd_24141-1814-PVC+30040P+0600_0_?productId=3133149&Ntt=sewer%20pipe&Ntk=i_products&pl=1&currentURL=/pl__0__s?Ntk=i_products$rpp=15$No=30$Ntt=sewer%20p ipe$identifier=

Which end is supposed to be in? It's not gasketed. Don't plan on solvent welding it to put lengths together. Drainage application.

I don't think Lowe's sells any gasketed SDR fittings.

cdad
Jul 3, 2010, 03:34 AM
Yes. Bell is the input side. Sorry I looked up the wrong stuff the first time. I saw the sdr35 and looked it up :)

KISS
Jul 3, 2010, 03:36 AM
Thanks.

speedball1
Jul 3, 2010, 06:38 AM
Rule of thumb for all fittings with a hub.
The flow goes from the male end into the hub. Good luck, Tom

KISS
Jul 3, 2010, 06:53 AM
Except when it's leaving a catch basin. :D