Ask Experts Questions for FREE Help!
 

Free Answers in 3 Easy Steps

Register Now
3 Steps
 


Ask QuestionsprogressAnswer QuestionsprogressBuild ReputationprogressBecome an Expert
 
At Ask Me Help Desk you can ask questions in any topic and have them answered for free by our experts. To ask questions or participate in answering them you must register for a free account. By registering you will be able to:
  • Get free answers from experts in any of our 300+ topics.
  • Accept money for answers that you provide.
  • Communicate privately with other members (PM).
  • See fewer ads.
  Answer this Question    Ask about Finance & Accounting    Ask about another Subject  
 

LingX
Jul 30, 2009, 06:12 AM
The system analysis consulting firm of Flow Associates is working on a
systems design project for Wind and Waves Surfing Gear, Inc.

Description Task Must Follow Expected Time (Days)

Draw Data Flow P None 9

Draw Decision Tree Q P 12

Revise Tree R Q 3

Write up Project S R, Z 7

Organize Data Dictionary T P 11

Do Output Prototype X None 8

Revise Output Design Y X 14

Design Database Z T, Y 5



a. Using the data from the table above, draw a Gantt chart to help Flow
Associates organize its design project.

b. When is it appropriate to use a Gantt chart? What are the
disadvantages? Explain in a paragraph.

c. Create a PERT diagram based on the data above. List all paths and
calculate and identify the critical paths.