Ask Experts Questions for FREE Help!
 

Free Answers in 3 Easy Steps

Register Now
3 Steps
 


Ask QuestionsprogressAnswer QuestionsprogressBuild ReputationprogressBecome an Expert
 
At Ask Me Help Desk you can ask questions in any topic and have them answered for free by our experts. To ask questions or participate in answering them you must register for a free account. By registering you will be able to:
  • Get free answers from experts in any of our 300+ topics.
  • Accept money for answers that you provide.
  • Communicate privately with other members (PM).
  • See fewer ads.
  Answer this Question    Ask about Finance & Accounting    Ask about another Subject  
 

cnl1404
Jul 27, 2009, 08:46 AM
For its inspecting cost pool, Hose Company expected overhead cost of $200,000 and 4,000 inspections. The actual overhead cost for that cost pool was $240,000 for 5,000 inspections. The activity-based overhead rate used to assign the costs of the inspecting cost pool to products is


$60 per inspection.


$48 per inspection.


$40 per inspection.


$50 per inspection

morgaine300
Jul 27, 2009, 09:54 PM
You figure ABC rates the same way you do traditional ones:
estimated overhead costs/estimated activity driver