rjh6325
May 5, 2008, 11:55 AM
During the most recent month at Lunistra Corporation, queue time was 4.5 days, inspection time was 0.8 day, process time was 1.9 days, wait time was 5.1 days, and ,ove time was 0.7 day.
Compute the throughput time.
Compute the manufacturing cycle efficiency (MCE)
What percentage of the production time is spent in non-value-added activites?
Compute the delivery cycle time.
Compute the throughput time.
Compute the manufacturing cycle efficiency (MCE)
What percentage of the production time is spent in non-value-added activites?
Compute the delivery cycle time.





